The Ministry of Public Works’ assistant undersecretary for road engineering affairs Ahmed AlHassan said 65 percent of the western part of Jamal Abdul-Nasser Road’s intersection is complete.
He added that two bridges will open in March and a third will open in April.
Hassan also noted that the project will be concluded by June 2018 at a total cost of KD 34.9 million.